Dairibord Zimbabwe — Factory Restructuring

Factory restructuring, warehouse expansion and Cascade Factory renovations for Dairibord Zimbabwe, Harare.

Industrial Structural Works
Completed
Contract Value USD 650,148.00
Client
Dairibord Zimbabwe
Location
116 Simon Mazorodze, Harare
Year
2025
Role
Contractor
Type
Warehouse & Factory Restructuring
Project Overview

Scope & Delivery

Taurus Civils (Pvt) Ltd successfully completed a major factory restructuring and expansion project for Dairibord Zimbabwe in 2025 involving the refurbishment of existing factory and warehouse facilities, construction of a new Finished Goods Warehouse and Bottle Storage Warehouse, and renovations to the new Cascade Factory. The works comprised demolitions, brickwork, plastering, tiling, painting, drainage installations, electrical works and associated civil works. Executed within an operational manufacturing environment, the project enhanced production efficiency, increased storage capacity and improved the overall functionality and operational flow of the facility while maintaining high standards of safety, quality and workmanship.

Solution: Phased industrial refurbishment within an operational manufacturing environment, balancing production continuity with expanded storage and improved facility flow.
Outcome: Completed factory restructuring enhancing production efficiency, storage capacity, and operational functionality.
  • Refurbishment of existing factory and warehouse facilities
  • Construction of a new Finished Goods Warehouse and Bottle Storage Warehouse
  • Renovations to the new Cascade Factory
  • Demolitions, brickwork, plastering, tiling and painting
  • Drainage installations, electrical works and associated civil works
2025

Year Completed

Project contracted and delivered in this year.

USD 650,148.00

Contract Value

Full contracted scope delivered to the agreed commercial and technical standard.

100%

Project Progress

Current delivery progress against the planned project programme.